Bayernwerke crews are locating and fixing a defective 20 kV underground cable after a short-lived outage.

Overview

  • The outage began around 21:35 on January 26 and affected roughly one-third of Ismaning.
  • About 3,000 households lost power, with the Fischerhäuser district particularly impacted.
  • Bayernwerke used switching operations to reroute supply, restoring most service in about 45 minutes.
  • All customers were reconnected by 23:36 according to the operator, while police reported full restoration around 23:00.
  • Two repair teams were deployed Tuesday morning to locate and repair the damaged line, with police citing a short circuit and the operator reporting two faults in the medium-voltage cable.