First Vivienda para el Bienestar Homes Handed Over in Morelia Under 82,000-Unit Michoacán Plan

A weekly delivery cadence signals the program’s shift from planning to execution.

Overview

  • Authorities delivered 48 of 144 completed homes in the Villas de Oriente development in Morelia, with units measuring 60 square meters and including two bedrooms, a full bathroom, kitchen, and living-dining area.
  • Michoacán’s package totals 82,000 homes financed with 49,200 million pesos, divided among 50,000 by Infonavit, 20,000 by Conavi, and 12,000 by FOVISSSTE.
  • Infonavit detailed a 2026 schedule for its 50,000-home commitment, reporting 6,000 already under construction, 18,000 starts in the first half of the year, and 24,000 in the second across multiple municipalities.
  • President Claudia Sheinbaum set weekly Wednesday handovers and said priority goes to workers earning up to two minimum wages, single mothers, and people with disabilities, with applicants registering through Infonavit.
  • Officials said roughly 100,000 difficult mortgages in Michoacán were restructured, and Conavi reported 894 Vivienda para el Bienestar units advancing in four municipalities of Nayarit with assignment by public draw.